Henan Jiuhuan Corporation has cooperated with Jiangsu Binxin Iron and Steel Group for many times

Author:Henan Jiuhuan Industrial Co. ,Release Time:2017-11-23

In the past two years, Henan Jiuhuan Industrial Development Co. , Ltd. has cooperated with Jiangsu Binxin Iron and Steel Group Co. , Ltd. many times, the two sides signed a contract for the sale and purchase of shaft furnace refractory materials, a contract for the spraying and maintenance of wear-resistant and high-temperature flue in the sintering plant, a contract for 2x12m2 shaft furnace body masonry refractory materials, and so on, the signing of these contracts has strengthened the communication and communication between the two companies, laid a solid foundation for the establishment of long-term cooperation between the two companies, and had a far-reaching impact on the development of both sides.

In June 2014, the parties signed a project for the supply and masonry of 2x12m2 shaft furnace bulk refractories, which commenced in mid-november 2014 and consists mainly of furnace masonry; the masonry of four shaft furnace combustion chambers, one drying chamber and two blast walls; Two Shaft Furnace Feeding Trough Pouring; shaft furnace shell of the internal thermal insulation spraying. As early as before the start of the project, in order to successfully deal with tight deadlines, heavy tasks, cross-operation, high-tech and other complex difficulties, my company well-planned, early deployment. Spare parts in advance, elaborate construction program, and detailed preparation of cold insulation plan, and strive to achieve security, quality, guarantee period, and strive to complete the construction task of the "three guarantees a competition" objectives.

At the beginning of the construction, we adjusted in time and planned as a whole according to the actual situation, and ensured the quality and time limit of the project by refining the project point again, optimizing the operation mechanism of the project management, etc. . At the same time, we aimed at the double goals and made concerted efforts, overcome rain and snow and other adverse factors, strive for the successful completion of the construction task. As of early February 2015, the project was successfully completed, and was highly recognized and praised by Jiangsu Binxin Steel Group Co. , Ltd. ! Based on the existing sound cooperation between the two sides, the two sides will further strengthen cooperation in the future development and win-win development!